Man days in animation studios: the calculation, and why the bid drifts from reality

Man days in animation studios: the formula, the calculation by role and phase, how many days a minute takes, and why the bid drifts from what you spend.

In short

  • The definition: one person’s work for one day. Ten days of effort can be ten days for one person or two days for five.
  • The calculation: volume to produce divided by the daily quota, role by role and phase by phase, never as a single total.
  • The minute: there is no public standard. Two Blender Foundation shorts work out at roughly 70 and 135 artist days per minute.
  • The budget: in 2025, an hour of animation supported by France’s CNC cost €896.6k on average, about €14,943 a minute.
  • The trap: a day of animation does not replace a day of comp. The gap shows up in a capacity plan by role.

The bid said 130 days. The project needed 142, and nobody can say where the other twelve came from. The division was right. What it was adding up was not.

What are man days in an animation studio?

A man day measures the amount of work one person delivers in one production day, whatever the date on the calendar.

Terminology bodies prefer the neutral person-day: the Quebec language office, for instance, lists man-day only as an associated term in its entry for the unit. Studios mostly say artist days. The maths is the same.

The basic formula fits on one line:

Man days = people × days worked

Effort and duration are two different things. Ten days of effort can be ten days for one person, or two days for five. The bid talks effort, the schedule talks duration. Most of the drift is born between the two.

Our position: a man day on its own means nothing. It only has value attached to a role and a phase.

See your artist days by role and by week.

New studios start with a trial, set up together remotely.

Book a demo

How do you calculate man days on an animation project?

You calculate a project’s effort by dividing, for each role, the volume to produce by that role’s daily quota.

Days for a role = volume ÷ daily quota

Volume is counted in the craft’s own unit: shots, seconds, assets. The quota is what one person in that role delivers per day on average, once approved, on your past projects. Only then do you add up.

Phase Volume Quota (assumption) Days
Layout 120 shots 6 shots a day 20
Animation 120 shots 1.5 shots a day 80
Comp 120 shots 4 shots a day 30
Total 130

Fictional quotas, to replace with yours. Method suggested by Whatdo.

The total of 130 serves the bid. For the schedule, it is almost useless: the comp team cannot do the 80 days of animation, and the reverse is just as true.

To get to weeks, divide each line by the role’s headcount and its real availability. Four full-time animators take four weeks to deliver 80 days. They are rarely full-time.

How many man days does a minute of animation take?

There is no public standard: depending on technique, style and finish, the figure can easily double.

Two open references give an order of magnitude. In a message dated 10 October 2010, Blender founder Ton Roosendaal shared his rough estimates for two Blender Foundation shorts. Big Buck Bunny: 5 artists for 7 months. Sintel: 10 artists for 10 months. He counts rendering over 600 and 888 seconds of film.

Film Length Artists Artist months Artist days per minute
Big Buck Bunny 10 min 5 for 7 months 35 70
Sintel 14.8 min 10 for 10 months 100 135

Whatdo’s calculation: artist months × 20 days ÷ minutes. Excludes developers, producer, script, music and rendering, which the message counts separately or leaves out.

Same software, same set-up, and nearly double per minute. The lesson is not a ratio to copy.

The other angle starts from the money. According to the CNC study of supported audiovisual production in 2025, France’s film agency puts the average hourly cost of supported animation at €896.6k. That is about €14,943 a minute. Divide it by your average loaded day rate to get a ceiling. At €350, an assumption for the calculation, a minute pays for 43 days at most, all spending included. That budget also covers writing, rights, music and studio overheads, so the artists’ share is smaller.

Your best reference is still your history: the real days of your last three projects, by role, divided by the minutes delivered.

Why does a bid drift from reality?

A bid drifts from reality because it adds up different crafts, counts everyone as full-time and forgets retakes.

Four mistakes turn up in almost every file:

  1. Crafts become interchangeable. The total hides that one role is short while another is waiting.
  2. A month has 22 days. A year has about 260 weekdays; take off 25 days of leave and around 8 public holidays, and you are left with about 227, under 19 a month.
  3. The lead is counted at 100%. They review, mentor and answer the director: their production day is worth half.
  4. Retakes do not exist. A quota is measured on approved shots, and every round of notes uses days the bid never saw.

A spreadsheet does the division without complaint. What it cannot see is the calendar of your other projects. The same animator is often already booked elsewhere in the week your bid counts them. One project’s days live in a tab; the whole slate’s days live in the head of the production manager.

Illustrative example: 3 roles, 6 weeks, 22 days short

A bid that is right in total can be 22 days short on a single role before the first delivery.

Role Bid Real capacity Real need Short
Layout 20 d 20 d 20 d 0
Animation 80 d 70 d 92 d 22 d
Comp 30 d 30 d 30 d 0
Total 130 d 120 d 142 d 22 d

The half-time lead removes 10 days: 3.5 people × 20 days make 70, not 80. Retakes add 12 days to the need. Animation is therefore 22 days short, more than six working days late for the team (22 ÷ 3.5). Comp starts that much later.

In total, the need is only 9% above the bid. The gap looks absorbable. It is not, because it falls on a single role.

Three answers remain. A freelance booking of 22 days costs €7,700 that the bid never held. Moving the delivery by a week and a half means a call to the client. Cutting the shot count is a talk with the director. The same check works before you say yes: test a new project in your capacity plan.

When is a spreadsheet no longer enough to track man days?

A spreadsheet is enough while one project occupies each role; it gives way when several projects share the same teams and the dates move every week.

The calculation stays simple. Keeping it current across the whole slate is much harder, especially when a phase slips and pushes its load onto the next. That is the whole subject of the animation pipeline.

Whatdo is the production planning tool for animation, VFX and game studios. It places your days by role and by week, shows overload before it arrives and the margin before you sign. Built with 24 studios over 18 months by founders who came through Wētā Digital, it sits above Kitsu or ftrack. It does not track shots or assets. A studio fills it in by hand or by CSV import. Its limit: without history, it calculates correctly on wrong quotas.

Try Whatdo for free on your own studio’s data.

New studios start with a trial, set up together remotely.

Try it for free

On your last project, which role used the most days outside the bid?

Key terms

Man day
The work one person delivers in one production day, also called a person-day.
Quota
What one person in a role delivers per day on average, once approved: shots, seconds or assets.
Load
The work to be done, expressed in days of effort.
Duration
The calendar time between the start and the end of a phase.
Bid against actuals
The role-by-role comparison between the days in the bid and the days really spent.

Frequently asked questions

How do you calculate man days?

Multiply the number of people by the number of days worked. For a bid, start from each role’s volume, divide it by that role’s daily quota, then add the roles together.

How many hours are in a working day in a bid?

Usually 7 or 8, depending on the studio’s convention. Write yours into the bid: 7-hour days and 8-hour days do not give the same total.

What is the difference between man days and working days?

Working days are dates on the calendar. They measure an amount of work. Twenty of them can fit into four working days if five people share the job.

How many man days does a minute of animation take?

There is no standard. Public figures from two Blender shorts give roughly 70 and 135 artist days per minute, excluding management. Your own history is the only reliable reference.

How do you turn days of effort into a schedule in weeks?

Divide each role’s days by that role’s headcount and by its real availability. Four animators available 90% of the time deliver 18 days a week, not 20.

Should you say man days or person-days?

Both mean the same unit. Person-days is the neutral form that terminology bodies prefer. Many studios simply say artist days in their bids.

Does Whatdo calculate days of effort by role?

Yes. Whatdo places each project’s days by role and by week across the whole slate. It does not track shots or assets: that stays with your production tracker.

Adrien Andivero
Adrien Andivero

CEO and co-founder of Whatdo, planning software for animation, VFX and game studios. Adrien worked at Wētā Digital before founding Whatdo.