Capacity planning template: can your studio take on a new project?
A capacity planning template for animation studios: the structure, the formulas and the method to know if you can take on a new project before you sign.
In short
- The question: a new project fits if its need sits inside each role’s remaining capacity, every week.
- The file: four tabs are enough: team, firm projects, new project, summary.
- The trap: a positive studio balance can hide 11 missing comp days.
- The position: do not weight uncertain projects, test scenarios.
- The answer: yes, yes from a given date, or yes at a given price, worked into the margin.
A client calls on Tuesday: can you start in March? You open the file, you ask the supervisor, and you answer “we should be able to”. That sentence commits the whole crew on the strength of a feeling.
How do you know if your studio can take on a new project?
A new project fits if its need sits inside the remaining capacity of each role, for every week of its production window.
The calculation fits on two lines:
Remaining capacity = role capacity - load already committed
Balance = remaining capacity - new project need
A positive balance leaves room. A negative balance puts a number of days on the gap. The reading order matters: role first, then week, never the whole studio.
A fast answer matters more than it did two years ago. France’s film agency, the CNC, reports in its study of the 2025 animation market that supported volume fell to 282 hours from 313 in 2024, with 8.1% fewer employees in the sector in 2024. Turning down a project is expensive. Accepting one you have no room for is expensive too.

What goes in a capacity planning template?
A useful capacity planning template fits in four tabs: the team, firm projects, the new project and a summary by role.
| Tab | Columns | What it works out |
|---|---|---|
| Team | role, people, share of time available | capacity per week |
| Firm | project, role, week, days | load already committed |
| New | role, week, days | need of the project under test |
| Summary | roles in rows, weeks in columns | balance by role and by week |
Grid suggested by Whatdo, to copy and adapt to your studio.
Capacity comes from a simple formula: people × 5 days × share of time available. Four compositors at 90% therefore deliver 18 days a week.
In the summary, committed load comes from a single formula, copied across the grid. Roles sit in column A, weeks in row 1:
=SUMIFS(Firm!D:D,Firm!B:B,$A2,Firm!C:C,B$1)
The days come from your bids. If the new project has no bid yet, estimate by phase and note the assumption next to the number. For capacity, our article on team capacity planning covers everything you need to take out.
How do you test a project in the file?
Test a project by adding its need by role to the firm projects, then reading the worst role in the worst week.
| In days | W1 | W2 | W3 | W4 |
|---|---|---|---|---|
| Comp, committed | 10 | 12 | 15 | 16 |
| Comp, remaining capacity | 8 | 6 | 3 | 2 |
| Comp, new project | 4 | 6 | 8 | 8 |
| Comp, balance | +4 | 0 | -5 | -6 |
| Animation, balance | +12 | +10 | +8 | +6 |
| Studio, balance | +16 | +10 | +3 | 0 |
The bottom line says yes: the studio never drops below zero. The comp line says no, with 11 days missing across W3 and W4. An animator cannot pick up a comp shot at short notice, so the animation surplus makes up for nothing.
The price of a yes becomes readable. At €400 a day, an assumption to replace with yours, those 11 days cost €4,400 in extra crew. You no longer have a feeling. You have an amount.
How do you count projects that are not signed yet?
Count unsigned projects in separate scenarios, and never weight their load by a probability of signature.
We have a firm view on this. A project with a 50% chance does not occupy half a compositor. It arrives or it does not. Weighting produces a plan that describes no real future, and it smooths out the very peaks you are looking for.
Instead, have the file read three versions:
- The base scenario: firm projects only.
- The test scenario: firm projects plus the new one.
- The busy scenario: the test scenario plus the other project under discussion.
In a spreadsheet, that means adding a “scenario” column to the New tab, then filtering. If all three say yes, say yes. If only the third one blocks, you know which project to wait for, and until when.
What do you tell the client, and when do you leave the spreadsheet?
Answer yes, yes from a given date, or yes at a given price: each answer comes straight from the balances in the file.
- Yes, if every role keeps a balance of zero or more.
- Yes from a given date, if a later start clears the gap. Then reread the following weeks.
- Yes at a given price, if the extra crew goes into the bid.
If none of the three holds, say no. A costed refusal beats a late project, and a client understands 11 missing days better than “it’s complicated”.
A spreadsheet does this job very well for one project at a time, with one person keeping the file. It starts to struggle when three projects share the same roles: every assumption needs a copy, and the copies drift apart. The file can also be wrong without showing it. On his page about spreadsheet audits, researcher Raymond Panko reports that five audits found important errors in 91% of 55 spreadsheets.
Whatdo, planning software for animation, VFX and game studios, compares these scenarios across the whole slate, by role and by week. It was built with 24 studios over 18 months and sits above Kitsu or ftrack. It does not track shots or assets. It is priced per studio, with unlimited users.

Which role in your studio would say no first?
Key terms
- Remaining capacity
- A role’s capacity for a week, minus the load already committed.
- Firm project
- A signed project whose load goes into the plan without conditions.
- Scenario
- A version of the capacity plan that adds or removes a project to read its effect.
- Production window
- The weeks in which a project needs a given role.
Frequently asked questions
How do you know if a studio can take on a new project?
Work out each role’s remaining capacity, week by week, then subtract the new project’s need. If a balance goes negative, the project does not fit as it stands: you have to move it, reinforce or reduce it.
What should a capacity planning template contain?
Four tabs are enough: the team and its capacity, firm projects, the new project, and a summary by role and by week. The summary is where you decide. The other three feed it.
Should you count a project that is not signed yet?
Yes, but in a separate scenario. Avoid weighting it by a probability, because a crew is either there or it is not. Compare the file with and without that project.
What is the difference between a capacity plan and a schedule?
The schedule says who works on what and when. The capacity plan checks that each role has time to do that work. Testing a new project relies mostly on the second.
When should you stop using a spreadsheet for capacity?
When several projects share the same roles and every question needs a copy of the file. With one project at a time and one person keeping the file, a spreadsheet works very well.
Do you have to leave Kitsu or ftrack to use Whatdo?
No. Whatdo does not track shots or assets. It sits above your tracker to plan people and margins.