Project profitability in animation studios: know your margin before you sign
Project profitability for animation studios: the formula to know a margin before signing, and why your studio’s schedule changes the answer.
In short
- The formula: margin is the signed price minus man-days by phase, freelancers and direct costs, worked out before you sign.
- The real trap: margin also depends on the studio’s other projects, which the bid cannot see.
- The context: France’s CNC reports producers carrying 24.1% of animation budgets in 2025.
- The decision: set a margin floor, then sign, renegotiate or walk away based on the real schedule.
- The tool: a spreadsheet is fine for one project; beyond that, see how Whatdo is priced.
The bid goes out, the client says yes, and everyone breathes. Three months later, comp is overflowing and the margin has melted without anyone deciding it should. The maths was right. It was done on a schedule that never existed.
How do you know a project’s margin before you sign it?
You know a project’s margin before signing by subtracting the cost of each phase, based on the studio’s real schedule, from the price.
This is the project profitability formula we recommend:
Margin = signed price − (man-days by phase × loaded day cost) − freelancers − direct costs
Divide the margin by the signed price to get a rate. Nothing clever there. The hard part is not the division, it is the man-days you feed into it.
A first check takes two minutes. Budget ÷ (weeks × 5 days × average day cost) tells you how many full-time people the budget can pay for. If the project needs more, you already have your answer.

This is not theory. France’s film agency, the CNC, publishes the numbers in its study of the 2025 animation market. The cost per hour falls 3.2% to €896,600. Supported volume drops from 313 to 282 hours. Producers carry 24.1% of budgets. Fewer hours, less money per hour, more risk on the studio: a badly costed project hurts more than it used to.
What goes into the cost of an animation project?
The cost of a project covers all production work, supervision, extra crew, technical costs and client review rounds.
| Item | How to cost it | What gets forgotten |
|---|---|---|
| Production, phase by phase | man-days × loaded day cost | retakes |
| Supervision and production | real time of supervisors and coordinators | counted as free, because already salaried |
| Freelancers | planned days × real rate | the unplanned booking |
| Licences, rendering, storage | real project cost | late-stage rendering |
| Client reviews | planned days per round | the extra round |
Grid suggested by Whatdo, to adapt to your studio.
A project profitability estimate rarely fails on production. Supervision is the line most often missing. A supervisor on a monthly salary looks free in a bid. They are not: their time on this show is missing from another.
Why does the spreadsheet flatter the margin?
The spreadsheet flatters the margin because it costs one project alone, while the studio is running several at once.
Your spreadsheet does this very well, right up to the day two projects want the same crew in the same week. It adds up correctly, provided the production schedule is reliable. It does not know your lead compositor is already booked in March, or that the current series slipped ten days.
That load always gets paid for somewhere:
- a freelancer, who often costs more than someone already on staff;
- a delay, so extra days on the project;
- an overloaded crew, then retakes.
None of those lines appears in the bid. All of them come out of the margin. Project profitability is decided on the studio’s schedule.
We watched this happen up close at Wētā Digital, on very large films: an ideal plan on one side, the reality of production on the other. Our story starts there.
What does a €50,000, 8-week project earn?
A €50,000 project over 8 weeks can earn a 20% or a 4% margin, depending on what is already running in the studio.
| Item | Studio available | Busy slate |
|---|---|---|
| Staff days | 100 × €400 = €40,000 | 80 × €400 = €32,000 |
| Freelancers | €0 | 20 × €550 = €11,000 |
| Slip | €0 | 12.5 × €400 = €5,000 |
| Total cost | €40,000 | €48,000 |
| Margin | €10,000 | €2,000 |
| Margin rate | 20% | 4% |
Same client, same price, same bid. Only the schedule changes, and the margin is divided by five.
Project profitability: when should you sign, renegotiate or walk away?
Sign if the margin holds on the real schedule, renegotiate if it only holds on the bid, and otherwise walk away.
Set your floor before you cost the job, not in front of the client. We will not give you a universal number: the CNC publishes no average margin, and your floor depends on your overheads. After that, the decision comes down to three cases:
- Margin above the floor on the real schedule: sign.
- Margin fine on the bid, but not on the schedule: renegotiate the date, the scope or the price.
- Margin below the floor either way: walk away, or accept it knowingly, for a strategic reason said out loud.
That third case matters. The French producers’ union AnimFrance described an unprecedented crisis in scale and duration in its statement of 20 November 2025. Taking a loss to keep a crew together can be defended. Finding out after delivery cannot.
Our view: if you run one project at a time, keep your spreadsheet. Whatdo, planning software for animation, VFX and game studios, helps when several projects share the same crew. It was built with 24 studios over 18 months and sits above Kitsu or ftrack. It does not track shots or assets.

So which project you signed this year would you have renegotiated, had you seen the whole slate?
Key terms
- Man-day
- A unit of workload: one person working for one day.
- Loaded day cost
- What a working day really costs the studio, including payroll charges.
- Slate
- All of a studio’s projects over a given period.
- Bid
- The price and scope a studio proposes to a client before the work is awarded.
Frequently asked questions
How do you calculate project profit?
Project profit is the signed price minus the total cost of the project. That cost adds man-days by phase multiplied by the loaded day cost, freelancers and direct costs.
What is the formula for profitability as a percentage?
Divide the margin by the signed price, then multiply by 100. A €50,000 project with a €10,000 margin has a 20% margin rate.
Is 20% a good margin for an animation studio?
We know of no reliable public benchmark. France’s CNC does not publish an average studio margin. Set your own floor from your overheads and your cash position.
Should salaried staff count in a project’s cost?
Yes. A salaried artist on one project is not available for another. Counting their time as free flatters the margin and hides the real cost of the decision.
How do you account for the studio’s other projects?
Place the new project on the schedule, week by week and role by role. Every overloaded week becomes a cost: a freelancer, retakes or a slip. Add that cost before you work out the margin.
Is a spreadsheet enough to work out the margin?
For one project at a time, yes. Once several projects share the same crew, you need to read the load across the whole slate, which a spreadsheet handles badly when the plan moves every week.
Do you have to leave Kitsu or ftrack to use Whatdo?
No. Whatdo does not track shots or assets. It sits above your production tracker to show the schedule, the load and the margin.
