Animation pipeline: the production stages, and who plans the handoffs

The animation pipeline explained for studios: stages and departments in 2D and 3D, where the pipeline breaks at the handoffs, and how to plan every step.

In short

  • The definition: the production pipeline is the order in which departments pass the work along, with what each one hands to the next.
  • The stages: pre-production, production, post-production. In 3D, assets and rigging weigh early; in 2D, animation and clean-up.
  • The weak point: the handoffs, where one department waits for the one before it.
  • The context: France’s CNC supported 282 hours of animation in 2025, 10% fewer than in 2024. Every lost week costs more.
  • The method: one delivery date per handoff, read every week in a reliable production schedule.

The rig arrives two weeks late. Nobody panics: animation will just start a little later. Eight weeks on, two projects need the same crew in the same week.

What is an animation pipeline?

An animation pipeline is the order in which a studio’s departments pass the work along, from writing to final delivery.

It splits into three phases: pre-production, production and post-production. Each department starts when the one before has delivered enough material to work with. That chain of dependencies is what makes it a pipeline rather than a to-do list.

The word covers two things. The technical pipeline is the tools, scripts and file formats: the pipeline TD’s job. The production pipeline is who does what, and when. This article is about the second.

Blender Studio, which documents its pipeline in the open, designs it for a small production unit of 10 to 20 people. It puts editorial and previz at the centre of every stage (pipeline design principles). That is the size of many independent studios, and a useful reminder: editing is not a final step, it comes back at every stage.

Our position: the technical pipeline is set once per project, the production pipeline is replanned every week.

See every stage of your slate, week by week.

New studios start with a trial, set up together remotely.

Book a demo

What are the stages of a 2D and 3D animation pipeline?

The stages run from writing to the master, and the gap between 2D and 3D lies mostly in what must be delivered before animation.

Stage 3D animation pipeline 2D animation pipeline What passes to the next
Writing and storyboard script, storyboard script, storyboard approved animatic
Design characters, sets, props model sheets, backgrounds approved designs
Assets modelling, surfacing, rigging cut-out rigs, or nothing in traditional 2D published assets
Layout camera, blocking layout, key poses locked shots
Animation character animation key animation, in-betweens, clean-up approved animation
Image FX, lighting, rendering colour, backgrounds in place rendered frames
Comp compositing compositing final shots
Finishing editing, grading, sound editing, grading, sound master

Breakdown suggested by Whatdo. Every studio names and cuts its stages its own way.

For the schedule, the column that matters is the last one. A department does not start on a date. It starts when it has received enough material.

In 3D, the assets line weighs heavily: until a character has a rig, nobody animates it. In traditional 2D, the load concentrates in animation and clean-up, which need the biggest teams. VFX and games follow the same logic with different steps.

Every stage is costed in artist days by role, then placed on weeks.

Where does the animation production pipeline break?

The pipeline breaks at the handoffs, where one department waits for the previous one and nobody holds both calendars at once.

Four mechanisms keep coming back:

  1. The partial delivery. Rigs arrive for three characters out of five, and animation starts with what it has.
  2. The step back. A director’s note sends an asset back to modelling, whose team is already on another project.
  3. The cascade. Each delay pushes the load downstream, often onto comp.
  4. The shared department. The same crew serves several projects, and its calendar is the sum of everyone else’s delays.

A schedule kept in a spreadsheet is read by project. The pipeline is read by department, across the whole slate. Two weeks of slip is one shifted row in a tab. In the studio, it is two projects fighting over the same animators.

That slip weighs more than it used to. According to the CNC study of supported audiovisual production in 2025, France’s film agency supported 282 hours of animation in 2025, 10% fewer than in 2024. Budgets fell to €252.6m. Fewer projects and tighter budgets: a crew left waiting costs more.

Illustrative example: a rig that slips by two weeks

Two weeks of delay on a rig can put the animation crew at 156% two months later, on another project.

Animation W9 W10 W11 W12 W13 W14
Original plan, load 40 d 40 d 30 d 30 d 30 d 30 d
Original plan, rate 89% 89% 67% 67% 67% 67%
After the slip, load 40 d 40 d 70 d 70 d 30 d 30 d
After the slip, rate 89% 89% 156% 156% 67% 67%

In weeks 11 and 12, the two projects ask 70 days of a crew that delivers 45. That is 25 days short each week, 50 in total.

The shot tracker shows Project A late and Project B on time. Yet the problem lands on Project B.

The information was there from week 3. That left eight weeks to choose:

  1. Book 50 days of freelance help, €17,500 outside the bid.
  2. Move Project B by two weeks, comp included.
  3. Ask rigging to deliver the main characters first, so Project A’s animation can start earlier.

None of these options is free. All of them cost less chosen in week 3 than suffered in week 11.

Who plans the handoffs, and with what tool?

Handoffs are planned at studio level, by the head of production, above the shot tracker.

The production tracker says where each shot stands. The schedule says who will be free, and when. The two complement each other, and it is the second that goes missing when the pipeline slips. If your shots are tracked in Kitsu or ftrack, Whatdo sits above them. To choose by situation, see which planning tool fits which studio.

Whatdo is the production planning tool for animation, VFX and game studios. It places every stage by role and by week across all your projects, and shows overload before it arrives. It was built with 24 studios over 18 months by founders who came through Wētā Digital. It does not manage files, versions or the technical pipeline. A studio fills it in by hand or by CSV import.

Try Whatdo for free on your own studio’s data.

New studios start with a trial, set up together remotely.

Try it for free

In your studio, which handoff still has no written date?

Key terms

Production pipeline
The order in which a studio’s departments pass the work along, from writing to delivery.
Handoff
The point where one department delivers what the next one needs to start.
Pipeline TD
The technical director who builds the studio’s tools and file conventions.
Animatic
The storyboard cut with sound, which fixes the length of each shot before production.
Bottleneck
The department whose delay holds up everything downstream of it.

Frequently asked questions

What is an animation pipeline?

It is the sequence of stages and departments that takes a film or series from writing to delivery. The word also covers the tools and file formats that link those stages.

What are the stages of an animation production pipeline?

Three phases: pre-production (writing, storyboard, animatic, design), production (assets, layout, animation, rendering) and post-production (comp, editing, grading, sound). Every studio cuts them its own way.

What is the difference between a 2D and a 3D animation pipeline?

In 3D, modelling and rigging must be delivered before animation can start. In traditional 2D, most of the load sits in animation, in-betweening and clean-up. The order of the phases stays the same.

What does a pipeline TD do?

The pipeline technical director builds the tools, scripts and conventions that move files from one department to the next. They own the technical pipeline, not the crew plan.

Who plans the pipeline in a studio?

The head of production, with each department’s supervisor. Coordinators follow progress; the dates of the handoffs are decided at studio level.

How long does each stage of the pipeline take?

There is no standard duration. Divide each stage’s volume by its role’s quota to get artist days, then by the available headcount to get weeks.

Does Whatdo manage the technical pipeline?

No. Whatdo does not manage files, versions or shot tracking. It plans the crew and the margin of each project, above your production tracker.