WhatdoBETA
Book 30 minutes
Book 30 min

VFX bidding: build the bid from the crew you actually have

VFX bidding from the crew up: turn a shot count into artist days, check the crew is free across overlapping shows, then track the bid against actuals.

In short

  • The method: VFX bidding starts from the shot count, sorted by complexity, then turned into artist days by department.
  • The formula: bid days = shots × days per shot, plus assets, supervision and contingency. The price comes after.
  • The trap: a bid that is right on paper goes wrong if comp is already booked on another show.
  • The tax context: in the UK, VFX costs can claim an enhanced 39% Audio-Visual Expenditure Credit from 1 April 2025, up from 34% (GOV.UK).
  • The follow-up: compare days spent with days bid on delivered shots every week, and read the gap in the project margin.

The client sends a 40-shot breakdown on a Tuesday and wants a number by Friday. The supervisor sorts the shots, production adds the days, and the bid goes out. Six weeks later, comp is booked on two shows at once.

What is VFX bidding?

VFX bidding is the work of pricing a project’s visual effects in artist days first, then in money.

It starts from a breakdown: the list of shots, with what each one needs. A Cartoon Brew piece built on the experience of VFX supervisor Mark Russell describes five steps, from the internal estimate to tracking bids. Shots are sorted into three tiers there: easy, medium, hard. The vendor then estimates artist hours per shot and per task, from matchmove to comp.

A bid never stays still. In a VFX Voice feature from July 2020, vendors describe rebidding every time the scope changes, over several rounds.

Our view: a bid is built from the crew you actually have, not just from the breakdown. A correct number of days is worth nothing if the artists are busy elsewhere when the shots land.

See your bid on the schedule.

The bid’s days, week by week, next to the shows you have already signed. New studios start with a trial.

Book a demo

How do you turn a shot count into artist days?

Multiply the shots in each category by the days each department needs, then add assets, supervision and contingency.

Bid days = Σ (shots × days per shot per department) + assets + supervision + contingency

The price only comes after: bid days × loaded day cost, plus direct costs and margin.

Step What you count Where the number comes from What gets forgotten
1. Sort the shots easy, medium, hard the supervisor’s breakdown shots added in the edit
2. Days per department matchmove, roto, anim, FX, lighting, comp your past shows review rounds
3. Assets modelling, texturing, rigging the shared asset list the asset used in one shot only
4. Supervision supervisor, leads, production their share of time on the show the lead counted at 100% in production
5. Contingency a reserve on risky shots your past gaps contingency spread flat on every shot
6. Price loaded day cost, direct costs your real costs render, storage, licences

Grid suggested by Whatdo, to adapt to your studio.

Days per shot appear in no public study. They come from your delivered shows: the days each department spent, divided by the number of shots in each category. Without that history, you bid on instinct.

Where the work is done also moves the number. In the UK, GOV.UK states that companies can claim an enhanced 39% rate of Audio-Visual Expenditure Credit on UK VFX costs from 1 April 2025, up from 34%. The 80% cap on qualifying costs no longer applies to them. A producer compares net bids, not gross prices.

Why does an accurate bid go wrong when shows overlap?

A bid is calculated show by show, while the artists are booked across several shows at the same time.

The bid spreadsheet answers “how many days?”. It does not say who, or which week. The crew plan for the other shows lives in another tab, sometimes another file. The client’s turnovers slip, and two shows want the same comp team in the same week.

Three signals should stop you before a bid goes out:

  1. The busiest department in the bid is already booked over the period.
  2. The turnover dates are not fixed yet.
  3. The bid assumes a full crew from week one.

Crew utilisation is read by department and by week, never as an average. A studio at 80% can hide a comp team at 130%. That is the whole point of team capacity planning by role.

Illustrative example: VFX bidding on a 40-shot show

A 40-shot bid can come to 455 artist days, including 144 comp days the crew cannot absorb if another show has them booked.

Line Calculation Days
Easy shots 20 × 3 d 60
Medium shots 14 × 9 d 126
Hard shots 6 × 24 d 144
Assets 2 × 15 d 30
Supervision 15% of 360 d 54
Contingency 10% of 414 d, rounded 41
Total 455

At £400 a day, the work costs £182,000 before direct costs and margin.

Now look at comp alone: 20 × 2 + 14 × 4 + 6 × 8 = 144 days over 8 weeks. The studio has 4 compositors at 90% available time, so 18 days a week and 144 days over the period. The number fits exactly.

Except that a signed show books 2 compositors for weeks 1 to 4. That leaves 36 days over those four weeks (2 × 5 × 0.9 × 4), then 72 days after. Total: 108 days for 144 needed. You are 36 days short, which is one freelancer at 4.5 days a week for 8 weeks.

The bid was right. The schedule was not. The studio promised shots its crew could not deliver on time, unless it paid for a booking the bid never included.

How do you track a VFX bid against actuals every week?

Every week, divide the days spent on delivered shots by the days bid for those same shots.

Bid hold = actual days on delivered shots ÷ bid days on those shots

At 100%, the bid holds. Above it, each shot costs more than planned. In the example, if the first 12 easy shots took 45 days instead of 36, the bid hold is 125%. Projected over all 20 easy shots, that line moves from 60 to 75 days. You know it in week 3, not on the invoice, and the gap shows straight away in the project margin.

This tracking needs two sources: actual days, often logged in your tracker or timesheets, and the bid. A spreadsheet does the reconciliation for one show. It breaks when three bids fight over the same compositors.

Whatdo is production planning software for animation, VFX and game studios. It places each project’s days, signed or still in bid, on the weeks and by role, and shows the margin before signature. It was built with 24 studios over 18 months by founders who came through Wētā Digital. It sits above Flow or ftrack, and does not track shots or assets: reconciling actual days stays in your tracker or timesheets. It is priced per studio, with unlimited users.

Try Whatdo for free on your own studio’s data.

New studios start with a trial, set up together remotely.

Try it for free

On your last bid, which department should you have looked at first?

Key terms

Bid
The visual effects quote for a project, worked out in artist days, then in money.
Shot count
The number of shots to deliver, the basis of the bid.
Crew plan
The artists planned by department and by week on a show.
Booking
Reserving an artist on a show for a given period.
Utilisation
The share of a team’s available time booked on projects.
Turnover
The client handing shots over to the studio, which starts the work.

Frequently asked questions

What is a bid in VFX?

It is the visual effects quote for a project. It starts from the shot breakdown, turns it into artist days by department, then into a price. It is redone every time the scope changes.

How do you estimate days per shot?

From your past shows. Divide the days each department spent on delivered shots by the number of shots in each category. Without that history, the bid rests on the supervisor’s instinct.

Should you bid per shot or on time spent?

Both are used. A per-shot price reassures the client, while time spent protects the studio when the scope moves. Either way, keep days per shot as the basis of the calculation.

How much contingency should a VFX bid carry?

We know of no reliable public benchmark. Work it out from your past gaps between bid and actuals, and apply it first to complex shots, where the risk sits.

How do tax incentives change a VFX bid?

They change the net cost the client compares. In the UK, GOV.UK states that UK VFX costs can claim an enhanced 39% rate of Audio-Visual Expenditure Credit from 1 April 2025, up from 34%.

What do you do when the client adds shots?

Rerun the calculation with the same assumptions: category, days per shot, supervision, contingency. A bid that writes down its assumptions gets recalculated instead of renegotiated.

Does Whatdo track VFX shots?

No. Whatdo does not track shots or assets. It places each project’s days on the weeks, by role, and shows the margin, above your production tracker.

Adrien Andivero
Adrien Andivero

CEO and co-founder of Whatdo, planning software for animation, VFX and game studios. Adrien worked at Wētā Digital before founding Whatdo.