Game development budget: staffing plan, burn and milestones
Game development budget from the team up: build the staffing plan phase by phase, work out monthly burn, cost a slipping milestone and defend it to a board.
In short
- The basis: a game budget is first a team, multiplied by months, multiplied by its loaded cost.
- The evidence: in the French industry barometer published by the CNC in October 2026, 93.2% of staff at responding studios are on permanent contracts, and 48.0% of companies report a loss.
- The tool: the staffing plan places roles month by month, phase by phase, before naming people.
- The number to watch: monthly burn, because every month a milestone slips costs a month of team.
- The defence: in front of a board, show what a slipping milestone costs, not just the total. The logic is the same as project margin.
The publisher wants the budget by Thursday. The game director has the backlog in Jira, the producer has a salary spreadsheet. Nobody has tied the two to the vertical slice date yet.
What goes into a game development budget?
A game development budget is mostly a team, multiplied by months, multiplied by its loaded cost.
The rest exists but weighs less: contractors, audio, localisation, external QA, licences, hardware. One formula is enough to start:
Budget = Σ (people per role × months × loaded monthly cost) + external services + overheads + contingency
France’s film and games agency, the CNC, published its latest video game industry barometer in October 2026, based on 107 companies. It confirms how much salaries weigh. In 2025, 93.2% of staff at responding studios are on permanent contracts. Tech roles make up 32.3% of headcount, art and audio 25.9%, design 16.2%. Half of the studios (50.5%) report an average budget per game under €500,000. And 48.0% of companies report a loss.
A salaried team costs the same every month, whether the game moves forward or not. Hence our view: a game development budget is read in months of team, not in money. Every month of delay costs the full burn.

See your team month by month.
The staffing plan and its cost, on your own projects. New studios start with a trial.
How do you build the staffing plan, phase by phase?
The staffing plan places the roles you need month by month, phase by phase, before naming anyone.
Each phase ends with a milestone. That milestone, not the calendar, should trigger hiring for the next phase.
| Phase | Exit milestone | Team | What the budget covers | The trap |
|---|---|---|---|---|
| Concept | pitch approved | small, generalists | throwaway prototypes | hiring before the pitch |
| Pre-production | pipeline and tools ready | one lead per discipline | tools, art direction | underestimating tools |
| Vertical slice | playable slice at final quality | first specialists | final-quality content | a slice that skips saving or performance |
| Production | content complete | full team | most of the burn | hiring before the slice is approved |
| Alpha, beta, certification | complete, stable game | more QA, team winding down | QA, certification, localisation | keeping the whole team to the end |
| Launch | release and first patches | reduced team | patches, support | forgetting post-launch |
Grid suggested by Whatdo, to adapt to your studio.
Build the table with roles in rows and months in columns. Names come later. A role without a name is a hire or a contractor to plan for, with a date.
The backlog and the staffing plan answer different questions. Jira says what is left to do. The staffing plan says who does it, when, and at what cost. Whatdo does not replace Jira or your backlog: it sits above them.
Why does monthly burn matter more than the total?
Monthly burn matters more than the total because delay is paid in months of team, and cash runs out month by month.
A spreadsheet adds up the lines and gives a total. It does not show what a slipping milestone costs. Nor does it show people shared between two projects. The CNC barometer reports that 36.4% of companies did work for hire in 2025. In those studios, the same developer moves between a client contract and the studio’s own game, and the staffing plan has to see both.
Two calculations are enough to steer:
- Monthly burn = the month’s team × loaded monthly cost + the month’s services and overheads.
- Months of runway = cash available ÷ monthly burn.
Then compare the date of the next payment with your months of runway. If the milestone lands after, the budget is wrong, even if the total is right.
Illustrative example: vertical slice, then production
A £1,897,500 project can take £198,000 more if the vertical slice slips by two months and the new hires arrive on schedule.
| Phase | Team | Months | Monthly burn | Cost |
|---|---|---|---|---|
| Vertical slice | 8 | 6 | £44,000 | £264,000 |
| Production | 18 | 14 | £99,000 | £1,386,000 |
| Salaries | 20 | £1,650,000 | ||
| Services (15%) | £247,500 | |||
| Total | £1,897,500 |
The slice slips by two months. The team of 8 carries on: 2 × 8 × £5,500 = £88,000. The 10 production hires still arrive on schedule in month 7, and wait for a slice that is not approved: 2 × 10 × £5,500 = £110,000. The delay costs £198,000, more than 10% of the budget, without a single extra line of content.
With a staffing plan tied to the milestone, those 10 hires follow the approval. The delay then costs only the slice team’s £88,000.
Tax credits do not change this reasoning. In the UK, HMRC guidance on Video Games Expenditure Credit says you can claim an expenditure credit at 34% of qualifying expenditure, which is capped at 80% of total core costs. The credit lowers the net cost of the game. It does not pay this month’s salaries.
How do you defend a game development budget to a board?
In front of a board, show the staffing plan by role and by month, the burn of each phase, and the cost of one month of delay.
A publisher, an investor or a funding panel first reads how credible the plan is. A total alone proves nothing. A staffing plan that ties every hire to a milestone, with the burn that follows, shows the studio knows what happens if the date moves. Add one line: “one month of delay in production costs £99,000”. It is often the line that reassures most, because it proves the risk is measured.
A spreadsheet holds this for one project and one version of the plan. It gets fragile when the slice date changes every month and the team also serves client contracts. Whatdo is production planning software for animation, VFX and game studios. It shows the team by role and by week across every project, and the margin before signature. It was built with 24 studios over 18 months by founders who came through Wētā Digital. It is priced per studio, with unlimited users.

Try Whatdo for free on your own studio’s data.
New studios start with a trial, set up together remotely.
If your next milestone slipped by a month, could you say today what it would cost?
Key terms
- Staffing plan
- The table of roles a project needs, month by month.
- Burn
- What the project spends each month, team and overheads included.
- Milestone
- A validated stage of development, often tied to a funding payment.
- Vertical slice
- A playable slice of the game at final quality.
- Loaded monthly cost
- A person’s gross salary plus employer costs, brought back to one month.
Frequently asked questions
How much does it cost to develop a video game?
It depends on the team and the duration. In the barometer published by France’s CNC in October 2026, 50.5% of responding studios report an average budget per game under €500,000, and 10.5% above €10 million.
What is a staffing plan in game development?
It is the table of roles the game needs, month by month. It is built by role before naming people, then multiplied by each role’s loaded monthly cost to give the budget.
What is burn rate for a game studio?
It is what the project spends each month: the team, contractors and overheads. Set against cash in the bank, it tells you how many months the studio can last before the next funding.
Why does the vertical slice weigh so much on the budget?
Because it is the proof used to fund production, and it measures how long content really takes to build. If it slips, the whole production team either waits or starts on an unproven base.
Do tax credits reduce a game budget?
They reduce the net cost, not the cash you need. In the UK, HMRC guidance says you can claim an expenditure credit at 34% of qualifying expenditure, capped at 80% of total core costs.
How much contingency should a game budget carry?
We know of no reliable public benchmark. Work it out from your past gaps between planned and reached milestones, then express it in months of burn.
Does Whatdo replace Jira or the backlog?
No. The backlog stays in Jira or your production tool. Whatdo places the team and its cost on the months, above that tracking, so you can see budget and load.